FAQ’s Kitchen and Ventilation Renovations 2023 Part 1

Compiled by Jill, Daphne
Updated June 7, 2023

Glossary
Scope of work. This means the contractual work and budget agreed to by the board, then agreed to by the members at a capital project GMM.
Change orders are added requests that have not been included in scope of work. The costs of these must be added to the agreed budget.

Who is responsible for the renovation

Homestarts is not managing the renovation, so members should not be calling the office looking for answers about the renovation or making complaints.

CMS Building Consultants supervises Winford Construction. Patrick Arendse is the Capital Projects Coordinator, an independent contractor, hired by the co-op and he works with CMS and reports to the board.

Why can’t I refuse this renovation?

Members may collectively own the Co-op as a whole; an individual co-op member does not privately own the unit they occupy. Members cannot opt out of capital project renovations or disrupt them, especially since the repairs are meant to prevent the further deterioration of co-op property.

Schedules

When will my renovation take place?

The project schedule has been posted in the lobby showing the date that your unit renovation will take place.  Merely find your unit number, then slide your finger over to the right to find your date. Please note that as the projects progress the schedules may be modified, so continue to check the lobby schedules for any changes.

How long will the renovation take?

The estimated work duration for the ventilation is approximately two weeks, and for the kitchens, up to three weeks. That being said, even when the active work has been completed there still may need to be another visit for inspection purposes and then for the drywall and painting to be finished.

Why is there weekend work by the contractors?

To deal with delays to the schedules, and in order to finish the entire project on time, Winford prefers to work through weekends. The Board has agreed that members may be asked if they will accept renovations to be done in their units on weekends but they have the right to refuse. Many members agree because they want the renovations to be done as quickly as possible.

Why are there changes to the project schedules?

Some changes are caused by supply chain delays of materials.
Some scheduled renovations do not take place due to unforeseen circumstances such as member  illness.

Some members have refused access to the contractors and the work is carried  forward causing disruptions to the schedule and a great expense to the co-op. Members refusing access may be charged for this extra work.

What is the schedule of work?

There are multiple units being done at the same time up and down the building.  Crew with different skill sets and credentials will renovate  part of the unit, then go to the next.  Later, they will come back to do some more and so on. Different crews work on the various steps of the project.

The basic steps involved for the ventilation are as follows: unit preparation, drywall cutting, duct work, electrical work, inspection, drywall repair, and painting. The painting will only be done in the areas directly affected by the work. It will be white in colour unless a paint of another colour is left available by the member(s) with instruction to use it.

Members can requisition the office in advance for their paint colour (1 gallon for kitchens and 1 pint for ventilation touch-ups.) Please be sure to have it ready by the time your renovation is being completed so that the workers can apply it. The office will provide you with the paint-chip book and you can notify them what colours you need.  The contractors will then paint the repaired area in your chosen colour.  The contractors will not paint other walls.

Members can expect at least two visits from Patrick and/or contractors for the ventilation, and three for the kitchen. Preliminary visits are necessary in order to take accurate measurements for the materials to be used.

Getting Ready

What am I supposed to do to get ready?

Be ready.  That means clearing areas before the contractors arrive and leaving an area at least 3’ clear under the bulkheads.

Kitchen Renovation:

1. The kitchen must be completely cleared of all personal belongings
2. Store all your belongings including any valuables, away from the work site.
3. Members must provide a clear path to the kitchen so workers can enter and work safely.

Please check your Kitchen Renovation Notice of Entry for all the details.

Kitchen Ventilation:

1. Clear the area/cabinets above the stove and cabinets where the bulkheads meet
2. Clear 3 feet of space under the bulkhead
3. Clear the floor of all tripping hazards

What about my appliances?

Your refrigerator will be moved into another area of your unit and plugged in for your use.  The fridge does not have to be completely emptied before it is moved, but please ensure that you remove anything that may spill or break. Check the fridge every night to make sure it is plugged overnight. The stove will be moved and will not be able to be used, but you may use the stove in the Penthouse Room.

Ventilation:

Bathroom:

1. Clear the area where the exhaust vent is located
2. Clear floor of all tripping hazards
3. Clear any personal items from countertops

The contractors will drape plastic over your sink and toilet area, which may be rolled-back for use at the end of the day.

Bedroom (in 1-bedroom apartments only):

1. Clear three feet from the wall under the bulkhead
2. Clear the closet area on the bulkhead side (You don’t need to completely clear the closet but keep in mind that there will be dust)
3. Clear a three feet path for the contractor to walk to the bulkhead

If you need help please contact Patrick to make arrangements.

The contractors will drape doorways leading into non-renovated areas.  It is recommended that members cover all furniture, computers and tv with plastic sheeting.

Living / Dining room:

1. Clear three feet from the wall that has a bulkhead
2. Clear all ornaments from that area
3. Clear all hanging picture frames from that area
4. Clear all tripping hazards from this area

Will the co-op provide me with any materials?

The co-op will provide you with boxes, bubble wrap and assistance, if requested. Contact Patrick  Arendse

Do I have to remove anything off the walls?

Please remove any paintings or ornaments that are hanging on the walls that might fall because of construction vibrations. Please store all valuables in a safe place while work is done. Sometimes, the workers may remove light fixtures if they are in the work-area. The co-op is not responsible for damage to belongings if they are not removed from the work area.

Will my carpets/rugs be protected?

Please clear the path from your front door to the areas where the ventilation work will be done. The contractors will lay sheeting over floors/rugs where they walk, which will be removed at the end of the day.

Can we lay our own materials over our carpets/rugs?

Members are welcome to lay their own materials to cover the floor, but they may not stand up to the frequent impact of heavy, steel-toed boots worn by the contractors. The workers do cover the floors that they walk on.

Doors and accessibility

Is my door locked when there is no work being done?

When the contractors are working intermittently in a unit, they will keep the door closed but unlocked. This is to allow them to work on several units together. The door is locked at the end of the work day, 6:00 p.m. to 6:30 p.m.  For your security and  comfort, you may want to ask a neighbour to check that your door is closed throughout the day if you’re not going to be there.

Members will be notified if the  workers are returning that day, or if no work is to be done on a day within the specified schedule.

Please note that the date on your Notice of Entry may be shifted to the next day if your unit is at the end of the assembly line of units being done on a given day.

What time does the renovation start and can I stay in my unit?

All members must provide access to the contractors between 9:00 a.m. and 6:00 p.m.  Any delays by the member results in weekend work, which is a “change order” and costs the Co-op (and subsequently, the member) money.  While you can stay in your unit, it is not recommended as the work is very noisy and dusty. The penthouse room is available for members.  Or you may ask your friends to stay at their place. The renovation ends each day at 6:00 p.m.

Can I go into the areas that are being renovated during the day?

No, for member safety, members may not go into the areas being renovated during the day. The Penthouse public space has been spruced up in order to offer it to members who may need to escape the noise and dust of the renovations. It comes equipped with appliances such as a microwave and coffee maker, as well as a fridge, stove, television, and wi-fi. It even comes with a binder of instructions of how to use the devices. There has been an additional kitchenette and furniture provided for your comfort and convenience.

What should I do with my pets?

All pets should be contained.

Pets are allowed in the penthouse room but must be on a leash and controlled at all times.

I’ve noticed that the elevators are often left on service – why is that?

On Monday, Tuesday and Friday, one elevator is put on service.  On Call will check the elevators after 6 p.m. and put the elevators back-in-service.

Safety Issues

Is there asbestos in my unit, specifically the popcorn ceiling?

There is asbestos in the popcorn ceilings but members should be aware that an analysis conducted a few years ago showed it is the lowest level. The majority of the ventilation renovations will not disturb the popcorn ceiling but sometimes, the contractors cut into it to accommodate the ventilation pipes.  The workers have received training in asbestos-handling and follow procedures before, during and after cutting.

ECOH (testing company) conducted tests in some townhouses in May 2023 and advised that there is no concern or hazard to the tenants with respect to asbestos fibres in the air as a result of the townhouse renovations . The fibre levels are well below the occupational exposure limit and the clearance limit under Ontario Regulation 278/05.

In the coming weeks there will be more ECOH asbestos testing in the midrise building as necessary.

Why do the contractors leave the bulkhead areas open?

The bulkhead areas are open while the work is being done and for the city inspection to approve. Inside the cavity, members can see the concrete ceiling and wall as well as pipes.  There are no contaminants inside the cavity. If you have any concern please contact Patrick

What about the dust?

The contractors will open windows and/or doors to aid ventilation during renovation.  The co-op will be providing air filter units to members with health issues that request them during their renovation. Air filter units will also be placed in the halls where the renovation work is taking place.  Recommendations for dealing with dust in individual units include opening windows and running fans that are directing the air toward the outdoors.

When the coring takes place (zoom boom outside units), there is significant dust, and it is strongly recommended that neighbouring units close their windows and stay inside from their balconies and terraces.

Once kitchen ventilation is finished, are rooms thoroughly vacuumed and stairwell and carpets shampooed?

Are kitchen cupboards hygienically clean for kitchen items to be reinserted or do we have to bring in a cleaner to clean and sanitize?

The crew, on completion, remove all drapes, trash and as much visible dust as possible. This is normal construction practice. Further thorough cleaning is not part of the scope of work.

Member Requests

I have an old dishwasher – can I use it in my new kitchen?

It is unlikely, as newer faucets do not match older equipment.  As part of the kitchen renovation, dishwasher connections are provided and capped-off for future installations should a member wish to install a dishwasher at a later date. Please contact Patrick

Why can’t I make changes to the plan for my unit?

Customization was not part of the project design because it increases costs substantially. The contracts (based on the member-approved budget) were signed last fall. Since then, an enormous amount of work by the engineer and the contractor has already taken place, and the contracts can’t be substantially altered without risking significant monetary and legal repercussions. Requests for customization from members also cause delays in the scheduled work. We urge members to refrain from making such requests.

Why are some members having extra work done?

There are three reasons:

1. Some members have requested disability accommodations which the co-op is legally obligated to process. Members must fill out an Accommodation Request form and submit it to the manager with supporting medical documentation. The board makes a final decision.

2. Each unit is individual and as the contractors are doing the work, they sometimes discover that changes need to be made. This may be moving an outlet, a change to a cabinet or a removal of a heating panel. These are added to the budget.

3.  Under Woodsworth’s Maintenance Bylaw, members have the right to request renovations to their units from the Board. These requests for changes must follow the procedures laid out in that Bylaw. Costs are assumed by the member, and an application to the City of Toronto for permits and inspections, as well as the Electrical Safety Association are needed for approval. The approval process can increase costs significantly because seemingly simple changes as upgrades must comply with ESA standards.  Needless to say, such requests disrupt the projects and cause delays. We urge members to wait until the end of the projects to make renovation requests.

Any such change orders which are outside the scope of work must be covered by the member.

Can the contractors help me?

No, the contractors are here to do the work, they are not here to answer member questions.  Please do not interfere with their time as that impacts the Co-op budget.  Address your questions to Patrick

Please note that Woodsworth has a legal duty to provide a safe work environment for all staff and contractors. Members must refrain from any threatening or harassing behaviour. They must also not violate the Human Rights Code. If members engage in discriminatory behaviour towards the workers, it puts Woodsworth at serious risk of legal action. The Board will swiftly address any reports of harassment or discrimination.

Deficiencies

There are some things incomplete in my renovation – what do I do about that?

All deficiencies should be reported to the Renovation Email address within two weeks of the completion of the renovation.  Deficiencies include such things as shelves missing, handles missing, holes in walls – anything that needs to be remedied.

Complaints

How do I lodge a complaint?
Send your complaint to renovation email address

What if I don’t use email?

How do we communicate with the project coordinator Patrick and/or the Renovations team?
In addition to email, members will have a pre renovation meeting with Patrick for measurements, to apprise the members of what they need to do to ready their unit and to answer any concerns.

If members have concerns but no email, Patrick is on site Mon.Tues.Wed.and Friday  afternoons and Thursday from 7.30am to 4pm. You may see him in the outer office on the second floor between his visits to units. If all else fails, you can write your question and put in office mailbox labeled ‘Attention Patrick’.

Some new questions may need to go to the Renovations team for discussion at the biweekly meetings. Patrick will pass those questions on to the team.  We will do our best to keep members informed via the Weekly

See also Part 2 of the FAQ.

Capital Projects Update, May 28, 2023

Update on kitchen and ventilation projects from the Board of Directors
The Weekly May 28, 2023

The scope of the kitchen and ventilation project has now reached the medium rise. There are understandably many questions from members regarding the work. Help is available for any members who request it, in order to prepare their homes for entry by contractors. Please notify the office if you require assistance in moving furniture or heavy objects. Materials such as plastic sheeting and boxes are also available from the Co-op on request. Patrick Arendse, our capital projects co-ordinator, is available to answer questions at 647-225-5796 or patrick.woodsworthcoop@gmail.com

Members are encouraged to contact the office as soon as possible to order paint for the affected areas of their units. There will be a form to fill out, and the paint colour should match what it had been just prior to the work commencing. For ventilation, only the areas where the work was done will be painted by the contractors, but the paint must be available upon their completion of the unit. For the kitchens, the room as a whole will be repainted.

An ad hoc committee has been formed to assist with communication around the project. The Board is pleased to welcome Jill MacDonald and Daphne Dutton as members of this new group to support members during the renovation process. They are making themselves aware of current and emerging issues, and will be an added resource for members with questions relating to how to prepare and what to expect in your units.

The Co-op is purchasing extra fans and air purifying filters to reduce the amount of dust in units and hallways of the medium rise.

The workers are engaged in up to five units simultaneously. For ventilation, there are seven main stages to the project: unit preparation, (areas to be cleared and items packed away), drywall cutting, duct work, electrical work, inspection, drywall repair, repainting. For both kitchen and ventilation, members can expect up to two weeks for completion, or if at all possible, fewer than 3 weeks.. It must be stressed that during this period, workers may not be present for the full working day and there may be days in which they will not enter at all. This is because of the multi-step complexity of the project. On days that your units will not be entered, an effort will be made to notify you that morning, although this cannot be guaranteed.

A significant reason for the length of time to complete work in individual units is due to the schedule of the municipal inspectors. Winford and CMS, (performing and overseeing the work), are making every effort to inform the inspectors well in advance of the estimated date of completion in any particular unit. However, the precise dates and times of the inspections are not within their control, and this may delay the final steps of drywall completion and painting. Please understand that the inspections are mandated and not optional. The Board and CMS/Winford are advocating to the building municipality to exercise as much expediency as possible, given the significant disruption to people’s units.

You can expect an estimate of two visits from Patrick Arendse and attendant professionals for the ventilation project, and 3 for the kitchen renovation. An appropriate notice of entry (48 hours) is expected for these visits. This is in order to enable them to assess the needs of your unit before work commences, and to evaluate its progress/results. Patrick, in addition to the written notifications from the office, will inform you of what items need to be moved or protected.

Any valuables, such as trinkets or potentially fragile wall hangings or windowsill items, should be secured in advance. Vibrations from the work may dislodge them, so please be mindful of any objects of sentimental or monetary value.

You may be home during the work, but there will be a significant degree of noise and dust. The Penthouse has been furnished and equipped for your comfort and respite during the turmoil, replete with a fridge, stove, coffee maker, tables, chairs, wifi, TV, and an instruction manual on how to use them.

The Co-op has arranged for the professional service of air quality testing both prior to and subsequent to work being done. In a test performed in a unit post-renovation, there was no detectable level of asbestos.

There is a lot of information to digest, and we realize that the nature of this work being done in our homes can create a great deal of stress and uncertainty. We feel it imperative to stress though, that the workers be treated with the respect to which we are all entitled. Any remarks or other behaviour which is abusive in nature can result in a notice to appear before the Board or open the Co-op to litigation under the Human Rights Code. We realize that the majority of members have not and do not engage in such behaviour, but it is incumbent on the Board to formally state our position.

 

Information meeting about kitchen and ventilation projects, Wed. Apr 26, 2023

There will be an information meeting on Wednesday April 26, 2023 at 7pm in the penthouse. The information session will be about the Kitchen and Ventilation projects at Woodsworth Co-op.

CMS, our engineering firm, Winford, our contractor and Patrick Arendse, Woodsworth’s Capital Projects Coordinator will be available to answer questions from members.

Sliding Doors Survey – 2-panel or 3-panel (2018)

Archived

GET READY TO VOTE FOR 2-PANEL or 3-PANEL SLIDING DOORS

Eligibility
Only members in the 1-bedroom units in the townhouses and the 3rd, 5th, and 7th floor units in the medium-rise are eligible to vote because they are the only members who will be affected by the choice. Your ballot offers three options: 2-panel / 3-panel / and /either one. We’d like all eligible units to vote – one vote per unit.

Ballots
110 eligible units will receive a sealed envelope with a ballot at the latest by Friday, March 16th, 2018.

Ballot Box
The ballot box will be in the second floor photocopy room, at the latest, by Friday, March 16th and will be removed on Tuesday, March 27. Someone in the office will sort and count the ballots and the majority decision will be posted on our web site and in The Weekly.

Pros and Cons
The choice of a 2-panel versus a 3-panel window will come down to how you want to use your space, whether saving money on hydro is an issue, and if air leakage is a problem for you.

Each panel of the three panels is about 32” wide. The middle panel opens; the two side panels are fixed (not movable). You can choose whether you want the handle of the middle panel on the right side or the left side. For those who now use or are planning to use a portal air conditioner, visualize where your air conditioner would be located and how its panel would fit into the window opening. Note that the new bedroom windows in the medium rise will be more suitable for a portable air conditioner.

A sunroom window with 3-panels will receive less wear and tear than a 2-panel window. The wear and tear of a 2-panel will slightly reduce the longevity of the sliding door and need some maintenance regarding seals and insulation sooner than a 3-panel design. Members experiencing difficulty opening our current 2-panel door will find the middle 3-panel lighter and easier to open. The 2-panel option has to be heavier because it has to push more window surface and support itself in a larger window opening.

There is less air leakage if a small one panel is movable and two panels are fixed. The air leakage through one large panel and one fixed will have some effect on your heating and cooling costs. Please be aware that you are only making your choice for the sliding doors now. Except for the east side of the building, the doors won’t be replaced until next year. We are presenting an option because CMS Building Consultants, the Project Manager, recommend the 3-panel option and members should weigh the pro and cons before voting.

Project Roll out
The project will run in two phases. The first phase will start on the north and east sides of the medium rise. The second phase will start in the south and west sides and 1-bedroom townhouse units. All street level and 2nd floor medium rise units will have their sliding doors assessed. If they need to be replaced, that will be done after we complete the upper storey sliding doors.

Quality of the Windows
The new windows will have thermal glass with a low-emission coating to keep UV rays and heat out. Argon gas between the panes regulates heat to keep outside heat out and inside heat in. That should make a big impact on your hydro costs.

Timelines
Billy Lai, our Project Manager, wants to get the tenders out in March and select a contractor in April.
Phase One would begin in July and last about three months.
Phase Two would begin in the summer of 2019.

Submitted by Valerie Veinotte,
Chair, 5-Year Capital Plan Group