Podium Deck Dec 18, 2025

December 18, 2025

Well, the project is winding down. Tomorrow will probably be the last day until the handrails arrive. These are expected between Christmas and New years. You will not be given notice of their arrival as the office is closed for a period of time and people are busy with holidays. You will just see workers coming to do the installation.

The fencing will remain up until the railings are installed.

We are sorry for the delay, but cannot control manufacturing in this case. The delay could be partly contributed to our late decision regarding the type of railing.

The stone splash pads in the Albert Franck garden will be reset when the soil removal people come to take down the level of soil in that garden.

The stones have been levelled. They are slightly raised in a few places but are expected to settle with use. If not, we will have that corrected in the future.

You are probably wondering about the pipes sticking out from the wall of the “tot lot” … they are the drainage pipes for the tot lot and are extended out to keep the water away from the wall of the lot. They were there before but shorter so we probably did not notice them. If they become problematic we can always have them cut down a bit. Maybe the tot lot sub committee can incorporate them into the overall design of the lot ( lol ). Reminds me of a space ship about to take off.

Anyway… that’s all folks.

Have a great holiday season
Mary
On behalf of the Board

Tot lot and podium deck completion

December 12, 2025 – From the Board 

Everything continues to go well. They will be finishing up a variety of things including the exit door floor in the breezeway, pointing, making sure the breezeway stones are flush, finishing with that back stairwell to the garage.

Everything should be finished up by next Thursday Dec. 18th. (Except possibly the railings).

There is a bit of a hold up with the railings. August is pushing for them to be here by end of next week but there is a chance they may not be here. They are still in the process of being made.

The front stairs cannot be used until the railings are on.

August will also move the two heavy items into place… the tree in the container by the wall of the staircase going down to the garage and the extra cement planter in the front of the co-op, to back by the landscape room.

  • From the Board, published in the Weekly, December 9, 2025

Good news: we’re expecting the Podium Deck project to be completed within the next week.

The main tasks remaining are pouring concrete in the Tot Lot, and installing the 42-inch-high fence. A railing will also be installed in the middle of the Breezeway front steps, as required by code.

At the same time, work is being completed on the Albert Franck gardens. The big drains are now unblocked. This week the contractors will dig out the soil around the drains, and add concrete splash blocks to disperse water away from the wall and ensure that it’s distributed effectively. The contractors will also dig out the tree stumps in the AF garden and the triangular bed in the walkway. A soil removal company will come this week to remove at least 1 foot of soil from the AF beds and also from the triangular bed.

The two garbage receptacles in the Breezeway will also be replaced, as they’re in pretty bad shape. New ones are being ordered. The two big flower containers at the bottom of the breezeway stairs will remain.

Midrise units with backyard patios – notice to members

Members in midrise units with backyard patios should have received a flyer last week, outlining the precautions needed to avoid damaging the new membrane. These include using planters and being careful not to cover up the drains, and, of course, not poking anything down into the patio surface. (If you haven’t got your flyer, contact the Office.)

A big thank you to Jill MacDonald who has had the foresight to help us think through the landscaping issues while this project was being carried out. What it means is that in the spring the gardens will be ready to go!! And thanks to all our members for your patience as we embarked on this monumental project.

Woodsworth Board of Directors

Tot lot fence decision and podium deck completion

From the Board of Directors, November 16, 2025

With time running out on the Podium Deck project, the Board has made a decision regarding the Tot Lot fence.

We received a large number of email submissions on this, split pretty evenly into the two obvious camps: a) those who were acutely aware of the security issues and wanted a total solution, and b) those who were much less concerned about security than accessibility and aesthetics.

The Board itself had no strong preference either way, and realized that there was no one solution that would satisfy everyone completely. So we’ve chosen a middle path that gives us flexibility to evolve over time.

For a start, we’re going with a 42-inch fence. It was felt that together with the 24- to 30-inch rise of the Tot Lot itself above ground level, this would provide a reasonable barrier to casual intrusions.

For now, no gate will be installed. The main reason for this is that any gate must be fully accessible, and therefore would need automatic actuation by fob, similar to the Lobby door. This would involve quite a bit of extra construction, and significant extra expense. So it makes sense to delay this measure for now. We can add a gate later if we can’t improve the security situation in other ways.

And there are quite a few other ways we can try.

Our 2024 Toronto Police CPTED (Crime Prevention Through Environmental Design) audit emphasized that the best way of discouraging intrusions is to make an area seem private and ‘lived in,’ through various simple changes to the environment. One option currently being investigated is lighting the Tot Lot in a way that will make it unattractive for illicit late-night activities.

Improvement ideas coming out of the Tot Lot committee will also be a big help. There are many ways we can make the Tot Lot a more useful gathering place, and the Police audit points out that frequent use by local residents is very effective in discouraging outsiders.

Finally, the Police audit recommends posting signs clearly establishing an area as private property. We have signs already, and these will be placed once Podium Deck construction is complete. We will continue to monitor security, and look at other safeguards as needed.

We thank all the members who submitted their thoughts on this project, and look forward to working with the Tot Lot committee to continue upgrading this important part of the co-op.

From the Board of Directors, December 7, 2025

Tot Lot Completion
Good news: we’re expecting the Podium Deck project to be completed within the next week.
The main tasks remaining are pouring concrete in the Tot Lot, and installing the 42-inch-high fence. A railing will also be installed in the middle of the Breezeway front steps, as required by code.

At the same time, work is being completed on the Albert Franck gardens. The big drains are now unblocked. This week the contractors will dig out the soil around the drains, and add concrete splash blocks to disperse water away from the wall and ensure that it’s distributed effectively. The contractors will also dig out the tree stumps in the AF garden and the triangular bed in the walkway. A soil removal company will come this week to remove at least 1 foot of soil from the AF beds and also from the triangular bed.

The two garbage receptacles in the Breezeway will also be replaced, as they’re in pretty bad shape. New ones are being ordered. The two big flower containers at the bottom of the breezeway stairs will remain.

Members in midrise units with backyard patios should have received a flyer last week, outlining the precautions needed to avoid damaging the new membrane. These include using planters and being careful not to cover up the drains, and, of course, not poking anything down into the patio surface. (If you haven’t got your flyer, contact the Office.)

A big thank you to Jill MacDonald who has had the foresight to help us think through the landscaping issues while this  project was being carried out. What it means is that in the spring the gardens will be ready to go!! And thanks to all our members for your patience as we embarked on this monumental project.

Update on the podium deck Nov 15, 2025

From the Board of Directors, November 15, 2025

As you can see the project is in the finishing stages. They still expect to complete the work by the end of November. There will be two things happening next week.

Monday and Tuesday the workers will be here laying all the remaining interlocking bricks and fixing the ones that they damaged during construction.

While they are laying the interlocking in the breezeway, there will be some minor disruptions at the front door. We have been assured that the workers will help members navigate through this.

They will also be starting the walls to the ramp for the tot lot.

Thanks as always for your patience during this project.

Plans for the ‘Tot Lot’

The Board of Directors has had some queries regarding plans for rebuilding of the ‘Tot Lot’, as part of the larger Podium Deck project. We’d like to clarify the situation, and ask the membership for input.

Yes, the Tot Lot will be rebuilt, better than ever. It will be surrounded by a fence of black-iron construction – 1/2-inch rails spaced 4 inches apart, similar to the rails on the sunroom balconies in the midrise. The area will be made accessible, with a proper ramp and fob-activated gate.

However, a question remains regarding the fence. There are two main options as far as height:

1. A low fence. We are informed that by code, the two-foot drop around the Tot Lot requires a fence at least 42 inches high. This would maintain the look of the space, but has a drawback of not providing any real security for the area, which has become a convenient stop for outsiders wandering through our neighborhood.

2. A taller fence, about 6 feet high. This would allow the Tot Lot to be secured against trespassers. It would also improve security for the adjoining patio areas belonging to Wilton Street units. However, it would alter the appearance of the area, and possibly look less inviting to our members.

For the Board, security has been an over-riding concern. Issues have lately included people sleeping in the Tot Lot space, keeping people in the units above awake with foul language, shooting up and leaving needles around, and using the alley as a washroom. Our recent police safety audit recommended creating strong demarcation of our property, with signs and physical barriers, such as fences.

Even so, there are clearly positives and negatives to both the shorter and taller fence options. Given that this fence will become a prominent feature of our Woodsworth environment, we want members to have every opportunity to voice opinions, or suggestions.

We’ll have to make a final decision soon, so please email any comments to our main Board address (Board@WooodsworthCoop.ca) within the next few days.

Woodsworth Board of Directors

SEE:  https://www.woodsworthcoop.ca/index.php/tot-lot-fence-decision/